Manufacturing / Power BI

    Finding the real bottleneck in a design-to-ship process

    Custom equipment manufacturer | Power BI + on-prem SQL Server + SharePoint

    All project numbers, stage names, and figures below are illustrative. Client data stays private.

    The Problem

    Projects were shipping late and nobody agreed on why. The prevailing assumption inside the company was that drawing approvals were the bottleneck, so that is where the improvement effort was going. Leadership wanted to review the full design and production process and find out which stage was actually causing the delays.

    The Solution

    We merged several data sources into a single schedule variance heat map. Actual dates came from the ERP system on an on-premise SQL Server, connected to the Power BI Service through a gateway. Budgeted dates, plus a few stages the ERP did not track, came in through SharePoint lists and Google Sheets. Every project shows the variance in days between the budgeted date and the actual date at each stage of the process, and the whole report filters by year, quarter, month, project manager, and project size.

    Explore a sanitized version of the report

    Stage averages (days vs. plan)

    Mech Design
    -1
    Elec Design
    2
    Design Approval
    -2
    Long-Lead Buy
    1
    Fab Release
    1
    Fabrication
    -1
    Paint/Finish
    1
    Assembly
    -8
    Functional Test
    -6
    Final Inspection
    -1
    Ship Prep
    0
    Ship
    -7

    Green = days ahead of plan. Red = days behind plan. Blank = stage not tracked for that project.

    Project NameMech DesignElec DesignDesign ApprovalLong-Lead BuyFab ReleaseFabricationPaint/FinishAssemblyFunctional TestFinal InspectionShip PrepShip
    P0001-873326-30-3-1
    P0002513-772-16-10-6-4-15
    P0003-205-5-417-7-4-26-11-3-8-16
    P0004-14-3-284-31-11-27-2
    P0005-3442530-3-8-73-2
    P0006710-4-7-76-344-7-8
    P0007-50-101-2-15-261-16-4-1-9
    P0008-1712-106107-26-15-117-23
    P0009-25-1-35-4-32-21-3
    P0010711-234-9-13-43-6-13
    P00119-1-140-14-44-12-112-2-8
    P001214-11-76442-3-3-3-6
    P0013-61165-24-10-512-5
    P001424-6511-64-2-6-1
    P001511-61-6-106-10-11217-7
    P00165-6-18-121-1616-9
    P0017-1-2040-5-3-2-8
    P0018-4-17-12-14-18-5-18-26-8-21
    P0019-2515223-72
    P0020-254-254112-14
    P00218631-3-2-26-236-1-21
    P0022-73-51235-447
    P0023172601-63-40
    P0024-3-3-2111-18-11-8-9-5-9

    The Results

    The heat map made the pattern hard to argue with. Drawing approvals, the assumed problem, were running close to schedule. The bottleneck actually started at assembly, and it got worse as projects got bigger: large projects were being under-estimated and took far longer than planned. The company stopped spending improvement effort on approvals and refocused on assembly estimating and capacity. Filter the demo above to Large projects and you will see the same thing they saw.

    Have a process everyone blames but nobody has measured? Start with a Reverse Solution diagnostic.

    Start the Conversation